Timelines Published · Updated · Bailey Nguyen · Founder, RagingMonk

What actually delays a venue opening

Almost never the build. The weeks disappear into approvals, certificates and other people's calendars, and all of them can be worked in parallel.

Handover is not the same milestone as trade

An operator signs for a tenancy and hears one date. There are two, and the distance between them is where the first surprise lives.

On one project the centre issued an estimated handover at the start of August and an estimated commencement of trade at the start of October. Nine weeks separate getting the keys from opening the doors, and every one of them was accounted for by fitout, approval and certification rather than by anything discretionary.

Both dates belong in the model from the day the lease is read, because the rent conversation, the hiring plan and the opening campaign all hang off the second one. Planning against the first produces a venue that is ready to trade and not permitted to.

The fitout period belongs to the landlord

It is granted, not negotiated, and it can be restated. On one tenancy the fitout period was corrected mid-correspondence from an earlier figure to ten weeks.

That correction is the point rather than the number. A duration that a landlord can revise is a duration to plan against and not one to bank a launch date on. The operator's exposure is that every downstream commitment already made against the earlier figure, from contractor mobilisation to a campaign start, now has to move, and contractors do not hold dates for free.

The defensible position is to treat the fitout period as an input that may change until it is confirmed in writing, and to keep the launch date derived from it rather than fixed alongside it.

The consultants nobody budgets for

A designer's scoping note on one project named four appointments the operator had not allowed for, and none of them are the builder's responsibility.

A town planner, to handle change of use and approved seat count, unless the landlord is carrying the development application. A BCA consultant. A hydraulic consultant. A mechanical consultant. Each is an appointment, each has a lead time, and each produces a document that something else is waiting on.

The delay they cause is rarely the work itself. It is that the appointment is made late, because it was never in the plan, and the document it produces sits on the critical path of an approval nobody realised it gated.

The occupation certificate is a checklist of other people's paperwork

Development consent, construction certificate and occupation certificate are three separate instruments, and they need not sit with the same party. On one project the landlord resolved the development application while the tenant carried the construction and occupation certificates.

The occupation certificate is the one that catches operators, because it is not a judgement about whether the venue looks finished. It is an assembly of documents produced by subcontractors: a fire safety certificate and a waterproofing certificate among them. The venue can be complete, staffed and stocked, and still not be permitted to open because a trade that left the site weeks ago has not returned a certificate.

Chasing those documents is a task with an owner, and if one has not been nominated the owner is the operator, discovering it in the final fortnight.

The licence usually outruns all of it

Every item above is measured in weeks. Licensing is measured in months, and it starts earlier than anything else on this list should.

On one project a variation to an existing licence, not a new application, ran from early March to late July. It is covered in full in why the licence, not the build, sets your opening date, and it is the single item most likely to be the binding constraint on an opening date.

Run the approvals in parallel

The largest recoverable saving in an opening programme is not speed of construction. It is refusing to run the approvals in series.

Consultant appointments are the clearest case. A town planner, a BCA consultant, a hydraulic consultant and a mechanical consultant can all be engaged while the design is still being drawn. Appointed then, their documents arrive as inputs. Appointed once an approval has stalled, the same documents arrive as the reason it stalled, and the lead time gets spent twice: once waiting for the appointment, once waiting for the work.

The certificate chain behaves the same way. The occupation certificate depends on documents produced by trades who will have finished and left, so the request for them belongs in the subcontract conversation at the start, not in a phone call in the final fortnight when the trade is already on another job.

What compresses, and what does not

Build programmes compress, expensively, by adding labour and running trades in parallel. Approvals do not. A regulator does not move faster because a lease has a date in it, and a certificate cannot be issued before the document it depends on exists.

So the only real lever is sequence. Every approval that can be started before handover should be, every consultant appointment should be made while the design is still being drawn, and the certificate chain should have a named owner from week one. An opening date set by a construction programme and then checked against the approvals is a date that will move. Set it the other way around.

Common questions

Straight answers.

Q01How far ahead should licensing start?

Before the fitout programme is locked, and earlier than most operators expect. On one project a variation to an existing licence took from early March to late July, which is longer than many fitouts and is not work that can be accelerated by spending more on it.

Q02Can an opening date be set at lease signing?

A target can. A commitment should wait for the fitout period to be confirmed in writing and for the approval path to be mapped, because both can move after signing and both sit upstream of the date.

Q03Who chases the certificates?

Somebody has to be named, in writing, before the build starts. The occupation certificate depends on documents from subcontractors who have already finished and left, and an unowned chase reliably becomes the operator's problem in the last fortnight.

Q04Does a delayed opening cost more than the lost trading?

Usually it costs in three places rather than one: the trading that does not happen, the commitments already made against the original date, and the launch campaign, which is the hardest to move because its value depends on landing in a window that has now shifted.

Q05Is the build ever the reason an opening slips?

It can be, and it is the one part of the programme that responds to money, through additional labour and trades run in parallel. Approvals do not respond to money at all, which is why they end up being the binding constraint even on projects where construction ran late.

Q06What should be started before handover?

Every approval that does not require possession of the site. Design approval, consultant appointments and the licensing path all sit in that category, and each one left until after handover spends fitout period on administration rather than on building.

Still deciding?

Tell us what you're building. We'll tell you if we can help.